District Court Reduces Potential Award by $300,000 in Declaratory Judgment Action
(August 2011) By Lindsey M. Brunk, Summer Associate
For more information, contact Paul
Farquharson.
Coutinho & Ferrostaal Inc. v. M/V Federal Rhine, et al.,
No. JFM-08-2222 (U.S. District Court for the District of Maryland, July, 29 2011) | View pdf
The Plaintiff filed a Complaint against the Defendant in
August of 2008, alleging that it had negligently transported, handled, and
stored steel pipe cargo. The Plaintiff alleged that its compensatory damages
reached $350,000.00. However, the Defendant, relying on a clause on its
warehouse receipt, requested that a declaratory judgment be entered that the
Plaintiff’s damages could not exceed $20,170.91.
Under Maryland law, because the Defendant was a
warehouseman, it is permitted to limit its liability by a term in its warehouse
receipt. Md. Code Ann., Com. Law § 7-204(b). Here, the Defendant argued that it
effectively limited its liability for any damages to the Plaintiff’s steel pipes
by providing on its warehouse receipt that damages were limited to ten (10)
times the provided monthly storage rate. The Plaintiff presented a series of
arguments for the liability limitation’s unenforceability, all of which were
rejected by the Court.
First, the Plaintiff argued that it never received the
full warehouse receipt, so it could not be held to its terms. The Court
considered two (2) factors: (1) the Plaintiff was a sophisticated business
and was thus held to a higher standard than members of the general public,
and (2) delivery and receipt is presumed if a material is properly mailed
and the sender can show that it mails the document in question as a part of
its ordinary business practices. Accordingly, the Court held that the
Plaintiff indeed had notice of the limitation clause on the warehouse
receipt.
Next, the Plaintiff argued that the parties had a
written contract, and the warehouse receipt could not supplement that
contract. However, the Fourth Circuit has explicitly held that a warehouse
receipt can supplement an existing contract with limited liability terms.
See Phillips Bros. v. Locust Indus., Inc., 760 F.2d 523, 525 (4th Cir.
1985). Accordingly, the Plaintiff’s argument in this regard failed.
Lastly, the Plaintiff claimed that the contract was
ambiguous and could not be enforced. The Court noted that a contract is only
ambiguous if a reasonably prudent person could interpret it in more than one
way. The Plaintiff argued that because there was a $500.00 per package
limitation in the Defendant’s tariff, that was different from the limitation
on the warehouse receipt, the warehouse receipt limitation could not be
enforced. Unfortunately for the Plaintiff, there was a federal regulation
that provided that a specific contract between a marine terminal operator
and another party supersedes a generic tariff. 46 C.F.R. § 525.2(a)(3).
Furthermore, the Court held that the tariff limitation did not even apply to
the Defendant’s storage liability, but instead, to another company’s
stevedoring liability. Because the Plaintiff was a sophisticated party, it
should have understood that the tariff limitation only applied to
stevedoring. Hence, the warehouse receipt provision was unambiguous as a
matter of law.
Because the Court held that the Plaintiff had notice of
the complete warehouse receipt, which was a valid and unambiguous part of
the contract, the Defendant’s Motion for a Declaratory Judgment was granted.
Damages were limited to $20,170.91.