Before trial, the City and MCI advised the trial court that
they had entered into a binding arbitration agreement to settle their dispute.
Consequently, the court severed the third party lawsuits and stayed the case
pending arbitration. The City and MCI stipulated that the arbitration
proceedings would address both liability and damages. They also stipulated that
either Judicial Arbitration Mediation Services ("JAMS") or AAA Complex
Commercial Arbitration ("AAA") rules would control the arbitration proceedings.
The parties agreed that at the conclusion of the arbitration, the court would
confirm the award, and enter judgment.
At arbitration, the City was victorious. On the issue of
liability, the arbitration panel found that the City had cause to terminate
MCI's performance of the wastewater treatment plant contract. On the issue of
damages, the arbitration panel found that the City was entitled to recover
$14,939,004 from MCI. Pursuant to the parties' stipulations prior to
arbitration, the district court entered an order confirming the arbitration
awards. The Court also entered Final Judgment under Fed. R. Civ. P. 54(b).
MCI appealed to the Fourth Circuit Court of Appeals, and
asserted three main arguments. The appellate court began by noting that its
authority to review arbitration awards was "among the narrowest known at law"
because "to allow full scrutiny of such awards would frustrate the purpose of
having arbitration at all—the quick resolution of disputes and the avoidance of
the expense and delay associated with litigation." MCI at *13.
MCI first argued that the district court erred by entering
Final Judgment under Fed. R. Civ. P. 54(b). MCI argued that Final Judgment was
not proper where third party claims still existed in the original lawsuit.
However, the Court pointed out that the claims involving the third parties had
been severed prior to arbitration. Those claims could still be litigated,
without any preclusive or prejudicial effect from the City and MCI's
arbitration. Fed. R. Civ. P. 54(b) permits a court to direct entry of Final
Judgment as to one or more parties in a multi-party claim. Therefore, the Court
concluded that there was no just reason for delaying the entry of judgment as
far as the City and MCI's claims against each other were concerned.
Next, MCI argued that the district court should have
vacated the liability award because it was obtained through "undue means." Under
the Federal Arbitration Act ("FAA"), a court may vacate an arbitration award if
the award was procured by corruption, fraud, or undue means. 9 U.S.C.A. § 10(a).
MCI accused the City of using undue means. MCI alleged that the City: 1)
misrepresented facts to the arbitration panel; 2) used facts that were outside
the record; and, 3) argued its principal argument in rebuttal so that MCI could
not respond. The Court observed that even if MCI's allegations were true, no
court had ever construed "undue means" to apply to "legally objectionable"
actions by counsel. MCI at *14. Additionally, the Court noticed that the undue
means must have been used by a party to "procure" the award. This meant that a
causal relationship must have existed between the undue means and the award. The
Court concluded that MCI failed to prove such a causal connection between the
City's alleged actions and the liability award.
Finally, MCI argued that the arbitration panel's award was
unreasoned. In the case of a reasoned award, the arbitration panel provides a
concise written statement of the reasons for the award. In the case of an
unreasoned award, the arbitration panel makes an award, but does not disclose
its reasoning. In this case, before arbitration, the parties consented to the
arbitration panel using either JAMS or AAA rules. The panel opted to use AAA
rules. Under AAA, the panel was not required to render a reasoned award unless
one of the parties requested a reasoned award, in writing, prior to the
appointment of the arbitrators. Because neither party requested a reasoned
award, the panel was not required to give one.
Ultimately, the Court of Appeals affirmed all decisions
made by the district court in certifying the arbitration award in favor of the
City.