Infinite Menus, Copyright 2006, OpenCube Inc. All Rights Reserved.

 

Standard Waiver of Subrogation Contract Language is Vague as to Duration

John L. Mattingly Constr. Co. v. Hartford Ins. Co., No. 144 (Md. July 27, 2010)

In this contract case the seminal issue centered around the interpretation of a form construction contract written by the AIA. In John L. Mattingly Constr. Co. v. Hartford Ins. Co., the Maryland Court of Appeals found the waiver of subrogation clause in that contract to be ambiguous as to whether or not the waiver ends when the builder completes construction. Therefore, the Court of Appeals remanded the case back to the Circuit Court of Calvert County to hold a trial on the temporal ending of the waiver clause.

In this case, K.B.K., Inc. ("K.B.K") hired John L. Mattingly Construction Co., Inc. ("Mattingly") to build an Arby's restaurant. The two parties signed a form contract drafted by the AIA. That contract contained a clause in which each party waived its right of subrogation for all claims arising out of the construction. It also mandated that K.B.K. acquire insurance to cover all losses on the property "arising out of the work." Over a year after Mattingly completed construction, the Arby's caught fire. K.B.K.'s insurance company, Hartford Underwriters Ins. Co. ("Hartford"), filed suit against Mattingly alleging, among other claims, negligence. The Circuit Court of Calvert County dismissed the case on Summary Judgment, claiming that the contract between K.B.K. and Mattingly unambiguously waived K.B.K.'s right of subrogation for all claims, including claims that arose after the completion of the construction. The Court of Special Appeals reversed and remanded. Mattingly appealed the Court of Special Appeal's decision to the Court of Appeals.

The Court of Appeals examined the waiver of subrogation clause to determine whether the language of the contract was unambiguous. That clause required K.B.K. to purchase insurance that covered all of "the work" performed by the builders. The contract defined "the work" as:

The construction and services required by the Contract Documents, whether completed or partially completed...The work may constitute the whole or a part of the project.

Using this definition, the Court of Appeals found that the first phrase, "construction and services required," clearly restricted the definition of "the work" to the time before construction was completed. However, the Court of Appeals found that the second phrase, "whether completed or partially completed," appears to extend the definition of "the work" beyond the completion of construction. The Court then found that the second sentence, "The work may constitute the whole or part of the project," could be reasonably construed either way. Therefore, due to the internal inconsistency of the definition, the Court of Appeals affirmed the Court of Special Appeal's decision and remanded the case to the trial court.


 Powered By SLEEPER Technologies, Inc Professional Web Design

An STI Site  | Web Design By SLEEPER Technologiesimage
Copyright © 5/17/2012 Semmes, Bowen & Semmes | All Rights Reserved | Reproduction in whole or in part
in any form or medium without the express written permission of Semmes Bowen & Semmes is prohibited.
Disclaimer and link information regarding this web site