Subsequently, BSB petitioned the Circuit Court for Baltimore
City to establish and enforce a mechanic's lien against Stewart's property. A
hearing was held shortly thereafter, at the conclusion of which the Circuit
Court ruled that because BSB had no home improvement license, it had no right to
enforce the contract or to establish a lien based on the contract. BSB appealed
to the Court of Special Appeals, arguing that it did in fact have a home
improvement license, or in the alternative, that it substantially complied with
state licensing requirements.
On appeal, BSB argued that it complied with state licensing
requirements because James Kunkel, a 50 percent owner of BSB, held a home
improvement license through a company called Stonehenge International, Inc
(Stonehenge). According to BSB, Stonehenge worked on Stewart's home inasmuch as
Mr. Kunkel, as representative of Stonehenge, oversaw and managed BSB projects.
The Court of Special Appeals, however, was not convinced.
Md. Code Ann., Bus. Reg. § 8-301 plainly states that all
entities or persons who contract to perform construction projects must have a
valid contractor's license. Because Stewart's particular project called for
improvements to his home, BSB was required to have a home improvement license.
While it is true that Stonehenge had such a license, BSB did not. Because BSB
was the one who contracted with Stewart, and because it did not have a home
improvement license at the time of contract formation, it did not comply with
the provisions of Section 8-301.
Nor did BSB substantially comply with state licensing
requirements. BSB argued that because one of its members who oversaw work in
Stewart's home had a home improvement license, the legislative purpose of
Section 8-301 was fulfilled because Stewart was protected against the
possibility of having an unskilled and financially irresponsible builder working
on his home. Instead, the Court held that the relationship between BSB, builder,
and Stonehenge, license holder, was too attenuated to be considered substantial
compliance.
The court distinguished both Maryland and other state cases
where the possibility of substantial compliance was found. For example, in
Dereggi Constr. Co. v. Mate, 130 Md. App. 648 (2000), the contractor procured a
license after the contract was executed but before any actual work began. The
case was remanded so that additional evidence could be produced concerning
whether the builder substantially complied with licensing requirements. In
another case, Jones v. Short, 696 P.2d 665 (Alaska 1985), the contractor filed
the necessary paperwork and paid the required filing fee before entering into
the contract. His insurance agent, however, failed to procure the necessary
insurance certificate. The contractor substantially complied with Alaska's
regulatory statute because his good-faith attempts "afforded the public the same
protection that strict compliance would offer." Finally, in Aesthetic Prop.
Maint., Inc. v. Capital Indem. Corp., 900 P.2d 1210 (Ariz. 1995), a contractor
substantially complied with Arizona licensing requirements when he moved to a
new address and filed the necessary paperwork. Although the Registrar of
Contractors erroneously sent a renewal notice to the contractor's old address,
it was through no fault of the contractor himself. Once the contractor
discovered that his license had expired, he immediately sought and received
reinstatement.
The common features in these cases, the Maryland Court of
Special Appeals noted, was that shortly after the contract was signed, the
contractor obtained a license, the owner was not prejudiced, and the purpose of
the statute was accomplished even though the contractor had not strictly
complied with the law. BSB, on the other hand, entered into a contract and began
work without a home improvement license, and further, BSB made no attempt to
cure its mistake before construction began. As a result, Stewart had no
assurances that the builder he hired was properly skilled or financially sound.
Most important, the Court added, was the fact that, in the
event Stewart suffered actual loss due to unsatisfactory workmanship by BSB, he
would be unable to recover from Maryland's Home Improvement Guaranty Fund, which
provides a remedy to homeowners who suffer actual loss "due to the act or
omission of a licensed contractor." Having denied Stewart a statutorily-created
remedy through no fault of his own, it would be inequitable to allow BSB to
maintain its own cause of action against Stewart. The Court therefore held that
BSB did not substantially comply with the provisions of Section 8-301, and the
mechanic's lien was unenforceable.
Baltimore St. Builders v. Stewart serves to remind all
Maryland construction contractors that compliance with state licensing
requirements is essential to doing business. Should a contractor decide to
proceed without obtaining a license, it may be unable to enforce a contract or
establish a mechanics lien against an owner who refuses payment. Courts will
only make exceptions if a contractor in good faith attempts to procure a license
before work begins pursuant to the construction contract.